Transfer Station: Community Meetings Schedule and Project Timeline

General Meetings:
Meeting # Date Time Location
1 04/20/08 11:00 p.m. - 12:30 p.m SCS Hall
2 04/21/08 7:00 p.m.- 8:30 p.m. SCS Hall
3 04/23/08 7:00 p.m.- 8:30 p.m. SCS Hall
4 04/25/08 7:00 p.m.- 8:30 p.m. SCS Hall
5 07/22/08 6:30 p.m.- 7:30 p.m. Council Chambers
6 08/26/08 7:00 p.m.- 8:00 p.m. Council Chambers
7 10/21/08 6:30 p.m.- 8:00 p.m. City Hall, Room 3A
8 11/14/08 7:00 p.m. Council Chambers
9 12/11/08 Rescheduled to January
10 04/30/09 6:00 p.m. Council Chambers
EIR Meetings:
Meeting Date Time Location
EIR Scoping Meeting - Begin Draft EIR 08/14/08 4:00 pm Council Chambers
Solid Waste Advisory Committee (SWAC) Site Meeting 07/07/09 11:00 am Council Chambers
Solid Waste Advisory Committee (SWAC) Site Meeting 07/14/09 11:00 am Council Chambers

Solid Waste Advisory Committee (SWAC) EIR Review Meeting

*Meeting Location:

County of Sacramento
Department of Water Quality
10545 Armstrong Avenue
1st Floor, Conference Room #170
Mather, CA  95655

08/04/09 11:30 am *
Planning Commission Draft EIR Hearing 08/06/09 6:30 pm Council Chambers
Planning Commission Final EIR Hearing 10/15/09 6:30 pm Council Chambers

General meetings (1-6) were identical in content and were designed to give the community an opportunity to identify concerns regarding the project and to talk with project and City staff. These meetings were not required by the EIR process and were not associated with the EIR.

EIR meetings as required by CEQA will be held in the coming months. Check back for announcements of upcoming EIR meetings, or click here to be added to the email list that announces updates to this project. Click here to learn more about CEQA.

For more information on community meetings contact the Transfer Station Project Manager, Bob Williamson, at (916) 478-2260 or bwilliamson@elkgrovecity.org.

Project Timeline

Below is a timeline showing a tentative schedule for this project. Additional information regarding the project background can be found by clicking here.

Preferred Site Selection  
1 Start of Transfer Station Project December-06
2 Residential Rate Adjustment - Fund Concept Work June-07
3 Review/Evaluate/Finalize Site Report January-08
4 Present Site Alternatives to City Council for Selection February-08
5 Council selects sites for Environmental Impact Report (EIR) evaluation February-08
6 City Council Reconsiders and Selects Site Alternatives for EIR Review. May-08
     
Concept Design / Environmental Review  
7 Complete Detailed Project Description Program September-08
8 Begin CEQA - Draft EIR Report August-08
9 Site Concept Design Evaluation Completed August-08
10 Issue EIR Notice of Preparation  August-08
11 Hold Public Information Hearings April-08 -  April-09
12 Issue Draft EIR for Public Comment June-09
13 End of Public Comment Period on Draft Report August-09
14 Planning Commission EIR Final Review  Aug.-Oct.-09
15 Public Hearing at City Council on EIR, Site Selection, and Project Financing Nov.-Dec.-09
     
Site Acquisition  
16 Apraisals, Negotiations for purchase of sites as directed by City Council Dec-09 - April-10
17 City Council considers Site Purchase Terms May-10
     
Project Design (Phase I) - Household Hazardous Waste Facility  
18 Start Project Design Process (begin to utilize State Grant funds) February-09
19 Finalize Site and Building Construction Documents April-11
     
 Phase I - Project Bidding and Construction  
20 Bid Site / Utilities / Building Work June-11
21 Start of Construction August-10
22 Complete Site / Utilities / Building Work August-12
23 Commence Project Commissioning Seotember-12
24 Commence Operations October-12

Requires free pdf reader. Printable version of schedule

This Schedule is subject to Change
Other phases of work including Transfer Station and Materials Recovery Facility are dependant upon actions and decisions following the Project EIR Review.